Posts in "Construction"
-
Contract Defeats Virginia’s Defense of Sovereign Immunity
A recent decision from the Supreme Court of Virginia established an important precedent for contractors doing business with the Commonwealth. The doctrine of sovereign immunity generally prevents parties from being able to sue the government when it is acting within the scope of its governmental authority, unless the government consents to suit. However, in Montalla, LLC v. Commonwealth, 303 Va. 150, 900 S.E.2d 290 (2024), the Court ruled that the Commonwealth cannot invoke sovereign immunity as a defense when the government enters into a valid contract through an authorized agent. This ruling affirms that when the Commonwealth enters into a legally binding contract, it must uphold its contractual obligations and allow contractors to pursue legal remedies, even without the government’s consent.
The dispute arose after a government contractor named NXL sought reimbursement for overhead costs under its contract with the Virginia Department of Transportation (“VDOT”). VDOT denied payment based on its interpretation of certain Federal Acquisition Regulations (“FAR”) provisions. NXL ultimately entered into an unfavorable settlement with VDOT based, in part, on this interpretation of the FAR. However, during settlement negotiations, VDOT received guidance from the Federal Highway Administration (“FHWA”) on the correct interpretation of the relevant FAR provisions. The FHWA’s interpretation confirmed that NXL was entitled to reimbursement. VDOT intended to adopt FHWA’s interpretation but withheld this information from NXL during settlement negotiations.
Thereafter, Montalla, LLC acquired NXL’s contracts with VDOT. Montalla, LLC discovered that VDOT withheld this information and sued VDOT seeking equitable rescission of NXL’s settlement agreement and recovery of contract damages. The trial court and Court of Appeals dismissed the case based on VDOT’s asserted defense of sovereign immunity. The Supreme Court of Virginia reversed. Although the Supreme Court noted that the doctrine of sovereign immunity is “alive and well” in Virginia, it ultimately found that the defense does not extend to actions based on valid contracts entered into by authorized agents of the government.
This decision strengthens protections for contractors and confirms that the Commonwealth of Virginia must uphold its contractual obligations. Moving forward, contractors should be cognizant of their ability to enforce their contractual rights against the Commonwealth.
-
Moore & Lee Secures Significant Settlement for Global Design and Engineering Firm in Signature Bridge Project Litigation
Miami, Florida – Moore & Lee is pleased to announce a decisive victory for our client, a leading design and engineering firm, in a high-stakes dispute with a design-build contractor involving an +$800 million signature bridge project in Miami, Florida. The case, litigated in the United States District Court for the Southern District of Florida, involved several complex factual claims and legal issues.
The design-build contractor sought over $405 million in damages, while Moore & Lee—led by partners Thomas Wilson and Robert Windus along with associates Zackary Rogers, Brandon Lee, and Kenny Rafter—pursued a counterclaim for non-payment of fees in excess of $30 million. After the Court granted motions for summary judgment filed on our client’s behalf, the firm secured a favorable settlement for our client.
Moore & Lee obtained Court rulings on dispositive motions that clarified multiple areas of Florida law, including the enforceability of contractual limitation of liability provisions for claims against individual design professionals, the statute of limitations applicable to claims concerning pursuit-phase services on design-build projects, and the function of the independent tort doctrine in states like Florida that have curtailed the economic loss rule. These rulings establish important legal precedent for future design-build projects in Florida and beyond.
-
Updates to FHWA’s Buy America Requirements for Manufactured Products
On January 14, 2025, the Department of Transportation’s Federal Highway Administration (FWHA) published a final rule erasing the long-standing Manufactured Products General Waiver to FHWA’s Buy America requirements. For more than four decades, the general waiver has allowed states and contractors to use foreign manufactured products on federally funded transportation projects. Under the FHWA’s new rule, (1) final assembly of manufactured products must occur in the United States (the “final assembly requirement”), and (2) components mined, produced, or manufactured in the United States must be greater than 55 percent of the total cost of the manufactured products (the “55 percent requirement”). FWHA will impose the new rule in two phases. The final assembly requirement will take effect for projects obligated on or after October 1, 2025. The 55 percent requirement will take effect for projects obligated on or after October 1, 2026.
During the rule’s public notice and comment period, commentators expressed concerns over increased cost and domestic availability of many manufactured products routinely used in federal-aid projects, such as lighting systems, Traffic Management Systems (TMS) equipment, Intelligent Transportation Systems (ITS) equipment, and rolling stock.
Going forward, contractors involved in federal-aid transportation projects should understand FHWA’s new rule and pay close attention to any updates to the rule. They should also discuss the new requirements with suppliers to ensure compliance with the requirements as they take effect on future federal-aid projects.
-
Virginia Enacts New Law Prohibiting “Pay-if-Paid” Clauses
Beginning January 1, 2023, “Pay-if-Paid” clauses will no longer be enforceable in public and private construction contracts in Virginia. “Pay-if-paid” provisions in construction contracts have long been enforceable under Virginia law. These conditional payment provisions are intended to protect general contractors from the risk of nonpayment by the owner by making the duty to make payment to subcontractors or downstream parties expressly conditioned on receipt of payment from the owner. Enacted on April 27, 2022, Senate Bill 550 is a bill that prohibits contractors on both private and public construction projects in Virginia from including provision in subcontracts that condition payment on the receipt of funds from the owner or high-tier contractor. SB 550 does not, however, prohibit a general contractor from issuing a back charge to a subcontractor for noncompliance with the terms of the subcontract as long as it notifies the subcontractor in writing of the intent to withhold and the reason for withholding payment. This new law is scheduled to take effect January 1, 2023.
-
What’s Your Excuse? COVID-19 and the Contractor’s Excusable Delay Claim
With the successful progress of the COVID-19 vaccine rollout, life in the U.S. is beginning to return to what many people will refer to as “the new normal.” While most of the country is preparing to return to “business as usual,” for those in the construction industry, business – for the most part – never really took a break from its usual pace. And while the regular pace of the construction industry is no stranger to delays and disputes arising from schedule disruptions, the construction industry, like many other industries, has and continues to face issues directly related to the COVID-19 pandemic. Such impacts include, for example, disruptions in the material supply chain, project site closures, and labor impacts. In the face of these unexpected new challenges directly resulting from the pandemic, those in the construction industry and particularly, construction lawyers, must consider whether such delays are excusable and, if so, whether they are entitled to compensation.
Whether a delay is excusable depends on the contract language and the circumstances surrounding the delay. For government contracts, the Excusable Delay clause (FAR 52.249-14) provides that any delay arising from “causes beyond the control and without the fault or negligence of the contractor” is excusable. The clause includes enumerated examples of circumstances that result in excusable delays like acts of God, fires, floods, epidemics, and even quarantine restrictions. Similarly, under the AIA’s Delays and Extensions of Time clause (section 8.3.1), a reasonable extension of time can be provided in circumstances where the delay was caused by something out of the contractor’s control like bad weather, labor disputes, or delivery delays. However, in order to be compensated for the delay under the FAR, the contractor must show that the Government was the sole and proximate cause of the delay. Likewise, under the standard AIA contract, the contractor must show that the owner solely caused the delay without any concurrent contractor delay. Examples of compensable delays include the Government’s failure to give timely work orders or an owner providing defective drawings; situations where the contractor can readily demonstrate that they had no fault in the delay.
In the case of the COVID-19 pandemic, it’s safe to say that such delays are beyond the reasonable control of and not reasonably anticipated by contractors. Still, that doesn’t necessarily mean that any delay in construction since the start of the pandemic in early 2020 can be deemed compensable or even excusable.
While there is no significant caselaw development specifically related to COVID-19 construction delays at this time, there’s plenty of guidance relating to government contracts from past unforeseeable events and their subsequent construction delays. In Ace Electrical Assoc’s, Inc., a contractor sought to change its termination for default into a termination for convenience by arguing that “a flu epidemic that had passed through its plant causing a 30% to 40% rate of absenteeism over a period of several weeks” had caused production delays. ASBCA No. 11781, 67-2 BCA ¶ 6,456. While accepting the notion that a flu epidemic could be cause for an excusable delay, the Board noted that the mere existence of a flu epidemic does not make a delay excusable per se. Id. Instead, the Board made clear that to establish an excused delay, the contractor must not only show the existence of the excusable cause for delay but also how the delay specifically affected the contractor, its work, and the efforts made to mitigate such delay. Id. Later, in Asa L. Shipman’s Sons, the Board faced a similar flu-related excusable delay claim and, in denying the contractor’s argument, made clear: “the essence of the ‘Ace Electronics’ test is the requirement that a defaulted contractor prove that an epidemic was the sole cause, not merely a contributing cause, of the performance delay.” GPOBCA No. 06-95, 1995 WL 818784 (Aug. 29, 1995). Similarly, in Crawford Development and Mfg. Co., a contractor maintained that its 4-week delay in production was caused by a flu epidemic that caused several key employees to become ill. ASBCA No. 17565, 74-2 BCA ¶ 10,660. The contractor’s records showed, however, that during the period the contractor was delayed, only two employees were absent and that the rest of the delay period was actually due to an industrial accident – not the flu epidemic. Id. Again, because the contractor failed to precisely establish how the flu epidemic materially affected its ability to perform, the Board denied the claim. Id.
Past flu epidemic excusable delay cases suggest that contractors claiming a delay in performance due to the COVID-19 pandemic should be prepared to establish, with specificity, how the pandemic directly caused their delays. Merely pointing to COVID-19 as a cause for delay will likely be insufficient, especially because – unlike past flu epidemics – the COVID-19 pandemic has impacted industries across the country for longer than just a few months. In other words, while certain Stay-at-Home Orders that did not identify construction workers as “essential” is likely cause for an excusable delay, lack of manpower due to employee illness may require more detail.
Legal precedent suggests, however, that contractors should not hold their breath for delay-related compensation. As mentioned earlier, the FAR and standard AIA contracts are very particular when it comes to a contractor’s right to delay-related compensation (i.e., the owner or government must be the sole cause of the delay to justify compensation). Contractors will have a difficult time arguing that delays resulting from COVID-19 were foreseeable by the government or owners in a way that would entitle them to compensation. In Pernix Serka JV c. Department of State, a contractor was unable to meet certain deadlines due to the Ebola virus outbreak in Sierra Leone. CBCA No. 5683, 20-1 BCA ¶ 37,589. The contractor was given time extensions by the government agency but was ultimately terminated due to the continued delays. Id. The contractor brought suit, seeking compensation for the costs it incurred to protect the health of its employees by arguing that the government agency’s expectation that work continue during the Ebola outbreak constituted a constructive and cardinal change. Id. The Civilian Board of Contract Appeals denied the claim, noting that the government agency never changed the scope of work expected of the contractor and that, even though the Ebola outbreak was unexpected, the government agency did not direct the contractor to make any changes as it related to the construction to justify compensation. Id. Using this example, contractors may be expected to show an actual owner or government ordered revision to the schedule or scope of work in lieu of the pandemic, which would then entitle the contractor to compensation. Additionally, contractors should note that any delay in their own project management during the pandemic may provide the government or owner with a concurrent delay counterclaim that could eliminate the ability to receive compensation.
In conclusion, contractors and their counsel should understand that COVID-19 related excusable delay claims must be equipped with detailed documentation that establish the causal link between the pandemic and the specific delays. Contractors should also be able to identify the precise ways in which they attempted to mitigate such delays in order to avert owner or government claims of concurrent delay. Moving forward, contractors should consider inserting more delay-related protective provisions and should consider expanding the definition of Force Majeure in their contracts to shield themselves from future problems associated with unforeseeable pandemics and the need for greater (and more costly) safety measures for their employees. As the country begins to reemerge from the chaos of the pandemic, we will likely see more caselaw specifically on these issues and continue to update our clients.
-
Attention Contractors – New Defense to Joint Liability Available
By now, most contractors are cognizant of the impact of Virginia Code § 11-4.6. Enacted in 2020, this statute allows general contractors to be liable if their subcontractors fail to properly pay their employees. In 2021, the General Assembly modified this statute and general contractors need to be aware of this revision.
The modified statute provides that a general contractor may provide a “certification” as evidence that they did not know, and had no reason to know, that their subcontractors were not paying their employees properly. The general contractor must obtain this certification, in writing, from their subcontractor, and the certification must be signed by the subcontractor under oath. The certification must also state that the subcontractor and its sub-subs, paid all of their employees all wages due for the work performed on the project. Construction companies should review this newly modified statute and update their subcontracts and lien waivers accordingly.
-
Moore & Lee Partners Robert M. Moore and Charlie C.H. Lee Recognized in Prominent Publication
Moore & Lee partners Robert M. Moore and Charlie C.H. Lee were recognized in the 28th Edition of The Best Lawyers in America©. Specifically, Mr. Moore and Mr. Lee were selected by their peers for recognition of their professional excellence in Construction Law and Construction Litigation.
-
Moore & Lee Partner Robert D. Windus Recognized in Prominent Construction Journal
Moore & Lee partner Robert D. Windus was recognized in the Official Educational Journal of the American Subcontractors Association, The Contractor’s Compass, for his peer review of the 2018 edition of Mechanical Contractors Association of America, Inc.’s (MCAA) publication Change Orders, Productivity, Overtime: A Primer for the Construction Industry. Specifically, Mr. Windus was credited for helping ensure that the content and data in 2018 edition was correct, reasonable, and applicable to the current state of construction management and construction law. The American Subcontractors Association recently joined the Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA) and the National Electrical Contractors Association (NECA) in announcing its full support and formal endorsement of the 2018 edition of MCAA’s publication. Read the full article here.
-
Moore & Lee Recognized by Chambers as a Top Construction Law Firm
Chambers and Partners recently recognized Moore & Lee, P.C. as “Band 1” for construction law firms in Virginia in 2018.
-
Robert D. Windus Lectures at National NEBB Conference
Robert Windus was a panel member lecturing at the National Environmental Balancing Bureau’s 2013 Annual Conference held May 2-4 in Montreal, Canada. The lecture panel addressed scheduling, testing, balancing and commissioning in addition to contracting and claims issues. In this interactive lecture, panel members engaged the 250 lecture attendees and addressed current pertinent industry issues involving testing, balancing, commissioning and contracting.